Need in 1 hour and 30 mins. 5 short essay questions for a project mgmt class
1. Compare and contrast top-down and bottom-up project estimating techniques.
2. You are comparing two projects. Using the data below, calculate the CV, SV, SPI, and CPI. Second, use the values to provide the status of each project. All values are in dollars.
Project A |
Project B |
|
EV |
850 |
550 |
PV |
875 |
575 |
AC |
900 |
650 |
3. What is the overall process of resource leveling on a project?
4. Compare and contrast leaders versus managers on a project.
5. Most projects completed using traditional project management are done in a weak matrix organization. Most projects completed in an agile project management framework use a strong matrix or pure project environment. Why is this so?