The table provides a project with the task lengths (in days) and precedence requirements, as well as

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.

Task

Length

Predecessor

Optimistic

Most Likely

Pessimistic

A

7

6.1

7

7.5

B

4

A

2.5

4

6

C

8

A

6.7

8

8.75

D

3

B, C

2

3

4.5

E

2

B

1.5

2

2.3

F

8

D, E

7.3

8

8.7

Which non-critical task should be monitored closely because of high completion time variance?

C
F
A
D
B
 