The table provides a project with the task lengths (in days) and precedence requirements, as well as
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
Task |
Length |
Predecessor |
Optimistic |
Most Likely |
Pessimistic |
A |
7 |
— |
6.1 |
7 |
7.5 |
B |
4 |
A |
2.5 |
4 |
6 |
C |
8 |
A |
6.7 |
8 |
8.75 |
D |
3 |
B, C |
2 |
3 |
4.5 |
E |
2 |
B |
1.5 |
2 |
2.3 |
F |
8 |
D, E |
7.3 |
8 |
8.7 |
Which non-critical task should be monitored closely because of high completion time variance?
C |
F |
A |
D |
B |
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code "Newclient" for a 15% Discount!
NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.