You have been asked to plan the following covert operation for the AIC Activity Duration (days) Most
You have been asked to plan the following covert operation for the AIC Activity Duration (days) Most Likely Immediate Optimistic Activity Pessimistic Predecessor 1 2 3 3 3 3 c B 4 6 8 2 6 9 12 7 D,C 10 G D 10 10 16 D.E 4 5 6 FGH 2 2 2. What is the probability of the project taking more than 25 days to complete? (In percentage and keep two decimal)